Change Orders

Forum Forums D-Tools General Forum Bugs Change Orders

This topic contains 4 replies, has 3 voices, and was last updated by  Joe Mason 2 months ago.

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #13147

    jimmy Wright
    Participant

    Internal Change orders modify the total price of the project. This shouldn’t be the case, as they are internal for parts not billed and add/deducts that change cost but not price.

    #13148

    jimmy Wright
    Participant

    Also change order cannot be deleted/edited/un-approved to fix price change issue. Once a contract is agreed on, we would use internals to make sure costing is correct for any add/deducts that the customer wouldn’t see. We would be using external change orders to modify the contracted price of the project, which the customer would have to approve.

    #13153

    Naresh
    Moderator

    Hi,

    We have a project setting
    “Mark added items as Non Billable on internal change orders”. You can mark that True.
    When items are added to internal CO they are marked Non Billable and will not impact price.

    Naresh

    #13248

    jimmy Wright
    Participant

    Approving an internal change order as approved, changes project total price.

    Case:
    Items were removed from scope, but should not have changed price due to negotiation with client (client error)
    When change order was approved with parts removed, project total was decreased.

    #13253

    Hi Jimmy,

    I am a D-Tools user. Would you please call me at (818) 612-5410?

    Thanks!

Viewing 5 posts - 1 through 5 (of 5 total)

You must be logged in to reply to this topic.